Forums › Kitchen DIY Forum › Kitchen DIY Advice › Schedule of work for kitchen fitting
This topic has 2 voices, contains 1 reply.
| Author | Posts |
|---|---|
| Author | Posts |
| December 8, 2005 at 11:28 am #6154 | |
|
robertc808 |
Hi, great website, hope someone can enlighten me here. We have bought a kitchen from Ikea and arranged through them to have it fitted. They put us in touch with one organisation but it turns out they subcontract to another. So from the word go I wasn’t entirely happy, as I would have preferred a single point of contact. Anyway, the guys turned up on Monday and were clueless about what to do so I am now concerned they are botching it. The work we are having done is as follows, and this is the order I believe it should be being done in: 1) Removal of old kitchen and tiles skimming position and removal of radiator to replace with plinth heater new kitchen and splashbacks and seal Job done! The order it is happening seems to be as follows: 1) Removal of old kitchen and tiles: Done and levelling of floor: Tiles are up but there is still a lot of cement on the floor. They are saying that’s OK existing plumbing to accommodate new sink position and removal of radiator to replace with plinth heater: Done all walls and make good: Not done – they are saying this is done after installation. Is that right? kitchen convinced that the floor shouldn’t be level before fitting the kitchen. I agree that a bit of screeding will be needed for the Karndean but the floor must be roughly level, surely? seal So my main concerns are: 1) They are saying that it doesn’t matter if the kitchen is installed on an uneven floor. I know the units have telescopic legs but I have a vision of these being cemented into the floor with screeding, as there is about 1/2cm of cement on the floor still! have though it would have made much more sense to do it before. I suppose there is less area to cover afterwards but won’t it be difficult to get it neatly rendered up to the wall units etc.? Sorry if some of this sounds a bit paranoid. I feel it will all come good but would just like some peace of mind and some expert advice. Thanks, Robert |
| December 8, 2005 at 4:53 pm #6157 | |
|
timfoley |
Robert, Welcome to the forum. Sorry to hear of your concerns here. To begin, I would say that to sub-contract need not be a negative and is fairly widespread in our industry. required it shouldn’t be an issue. The work we are having done is as follows, and this is the order I believe it should be being done in: before walls are plastered and I’m certain your plasterer would agree with me here, providing, of course, that he has access to an a temporary water feed. The flooring will require levelling prior to floor laying although after initial levelling compound has set, the cabinets can be fitted. Plastering, particulary if a paint finish is required, needs to take place prior to installation. replastered – behind cabinets. plasterers would find it difficult to achieve a good finish above the wall units. installers before they go ahead with their own schedule. Let us know how you go on here Robert. Tim |
You must be logged in to reply to this topic.







